De Lacy Academy Project

De Lacy Academy Project

A S Sports Systems Limited were pleased to be awarded the tender in February 2020 by Labosport, for De Lacy Academy part of the Delta Academies Trust.

Due to the Covid-19 pandemic works were unable to commence as planned. However as soon as it was safe to return to work, with all the correct measures in place in accordance with Government Guidelines.

Therefore works commenced in July. 

Before…De Lacy b4

In accordance with the Tender Specification works were “To uplift, remove and transport from site the existing synthetic turf surface.”

Removal…

The removal is completed with the aid of a excavator and telehandler, the team manually roll, band and clip the existing surface into manageable sized pieces for transportation…

A S Sports Systems Limited hold a waste carriers licence and only ever work with other organisations that comply with the Environment Agency. Re-purposing materials where possible to avoid them going to landfill.

Base preparation…

Upon removal of the existing synthetic surface, localized areas of the base stone were re-graded as required, before passing a straight level test.

Installation…

The installation aspect of the Project was “To resurface the Artificial Grass Pitch (AGP) with a 60mm 3G pile for Football use, to FA standards.

A S Sports systems Limited supplied and Install CC Grass Ultimate 60X-13 – Model Ultimate-6004B160-BL”.

Line Markings…

This included the supply and installation of permanent inlaid 100mm wide, line markings for Football a 1 x 11v11, 1 x 9v9 and 3 x 7v7.

Also the supply and installation of silica sand and SBR rubber infill, as per manufacturers guidance. Both products were evenly distributed and brushed into the finished pile.

Infill…

The surface area was 106m x 71m a Total of 7,526 square metres.

Included within this contract we arranged ball-stop perimeter fencing repairs and upgrades to be completed by https://www.blfencing.co.uk/.

The fencing remedial works were completed by introducing bracing posts along the fencing exterior.

Upon completion…

The system was tested by Labosport upon completion to ‘Football Association’ (FA) standards. The system passed FA testing, before being handed over to Delta Academies Trust within the 5 week schedule.

The testing was completed by https://labosport.com/ 

We supplied and installed Ultimate 60X-13 – Model Ultimate-6004B160-BL for futher information on this or other Products available please feel free to visit https://www.ccgrass.com/

We issued an O&M manual which included full product information with data sheets, warranty, maintenance guide and waste transfer information. 

For further information on Delta  Academies Trust, the different academies inc. the services and facilities they offer, please visit https://www.deltatrust.org.uk/our-academies

Should you be interested in a new or refurbishment of an existing school or any other sports pitch… Please do not hesitate to contact us https://www.as-sportssystems.co.uk/

#FA #FootballAssociation #Delta #Academy #3G #Football #Re-Surface

Contact Us

Have a quick question? Send us an email and we'll get back to you ASAP. Thank you.

Start typing and press Enter to search